I. Project Name and Tender Description

1 Project Name: Bidding for Ground-Source Heat Pump System – Hebei Branch, Leshou Agricultural and Pastoral Group Co., Ltd.

2 This tender is for the company’s geothermal heat pump project and will be conducted in accordance with the company’s procurement bidding system. The equipment supplier selected through the bidding process will then sign a formal procurement and construction contract with the company.

3 , Procurement Details, Bidding Requirements

Tender requirements for the geothermal heat pump system and heating/air conditioning renovation of the Leshou Agricultural & Pastoral Group's office building: Construction schedule requirements: 2022 Year 5 Month 1 Day ------2022 Year 6 Month 1 Day

Quality standards: Equipment and piping installations must meet current national construction and acceptance criteria, with the office building maintaining a summer cooling temperature no higher than 20 Celsius, with winter heating no lower than 22 Celsius.

Material requirement: Use a single pipe for the vertical buried tubes of the heat exchanger. U Plate heat exchanger, with tubing made of PE100 High-density polyethylene pipes, raw material pipes, as well as all other well pipes, connecting pipes, and crossing pipes are made entirely of this material. PE Pipe—raw material pipe—with a pressure-bearing capacity of 1.6Mpa , the ground-source circulating pump is selected from the Southern Pump Industry brand.

For other specific requirements, please refer to the attachment.

  • Bidding Method: Open Tender
  • Bidding Documents

4.1 Preparing the bidding documents

Bidders are required to carefully read all sections of the tender documents, submit a complete bid package, and ensure its authenticity. Any non-authentic bid documents will be deemed invalid.

4.2 Bid Document Format

Bidding applicants must submit their tender documents using the format provided in the tender documents.

4.3 Composition of the Bid Document

The bid document should include the following sections; please refer to the bid document format for specific content and writing guidelines:

1 Bid Letter  2 Letter of Authorization from the Legal Representative; 3 • Introduction to geothermal heat pump products, project design, and construction organization plans; 4 • Bidder qualification documents and inspection reports (with official company seal); 5 • Company Overview, Company Achievements, and Case Studies of Installed Partner Clients.

4.4 The bidding document should be submitted as A4 Specifications bound into a volume;

4.5 Number of copies and signing of the bidding documents

The bid documents should be submitted in duplicate, with one original and one copy. In case of any discrepancies between the original and the copy, the original document shall prevail.

  • Bid Document Format

 

5.1 Bid Letter

Leshou Agricultural and Pastoral Group Co., Ltd. – Hebei Branch:

Your proposal regarding    The tender requirements, now authorized Document number : Representative Submit the original bid documents 1 Copies and duplicates 3 Portion ( Including all the documents required by the tender documentation )

According to this letter, the signatory representative hereby declares agreement to the following: :

Prices listed in the attached bid quotation form.

We have thoroughly reviewed your company’s procurement and acceptance criteria for ground-source heat pumps, and we are pleased to submit our bid in accordance with the relevant provisions outlined in your standards.

We are willing to provide all the documents and materials required by the tender documents, and we guarantee that these materials are authentic, complete, valid, and legally compliant.

We will strictly fulfill all commitments and responsibilities outlined in this bid document, and comply with all provisions and requirements for bidders specified in the tender documents.

We fully understand that the tenderer reserves the right to accept or reject any bid at any time before awarding the contract, based on the evaluation committee’s recommendations—and we also fully acknowledge that the tenderer is under no obligation to provide an explanation for this decision.

We fully understand that the tenderer may not necessarily accept the lowest bid.

We hereby commit that all confidential matters involved in this bidding process will not be disclosed to any third party. Otherwise, you will bear all legal responsibilities.

If we win the bid, we will deliver and install the goods according to the timeline specified in the contract after signing it. We will also fulfill our responsibilities and obligations as outlined in both the tender documents and the contract.

Bidding Entity (Official Seal):

Legal Representative (Signature or Seal):

Date:

5.2 Letter of Authorization from the Legal Representative

HeShou Agricultural and Pastoral Group Co., Ltd. – Hebei Branch :

This Power of Attorney Statement : I am a... The company’s legal representative, acting as the company’s authorized agent, will participate in the bid for the geothermal heat pump project of the Hebei Branch of Leshou Agricultural and Pastoral Group Co., Ltd., on behalf of the company. The company fully acknowledges all documents signed and all matters handled during the bid opening, evaluation, negotiations, contract signing, and contract performance processes—provided they are directly related to this tender.

Bidding Entity (Official Seal):

Legal Representative (Signature or Seal):

ID number:

Date:

5.3 Product introduction of ground-source heat pumps, solution design, and construction organization plan

1 – Introduction to the Performance of the Company’s Ground-Source Heat Pump Products

2 • Customized scheme design and construction organization plan tailored for our company

3 Project Benefit Analysis

4 Utilize the existing heat pump units, remove the original water-source equipment, and install a ground-source circulation pump along with the corresponding配套 piping components.

5.4 Quotation Document

Company product quotations (including taxes, shipping costs, equipment installation and commissioning fees, etc.), bid quotation lists, and other preferential policies. Payment terms: Upon completion of the project and acceptance by Party A, and after Party B provides the full invoice for the total project cost, Party A will then make payment to Party B. 95% Construction payment, representing the remaining portion of the total project cost 5% As a warranty deposit, it will be fully paid two years after Party A approves the acceptance, provided there are no quality issues during this period.

5.5 Bidder qualification documents and inspection reports (with official seal affixed);

Relevant production qualifications of the bidding party, product testing reports from professional institutions, and more;

5.6 Company overview, company achievements, and case studies of installed partner clients.

Company Overview; Key Related Production Equipment; Current Production and Management Status of the Company; Existing Quality Management Practices at the Company; Company's Production Capacity And Corporate achievements, Cooperative suppliers, case studies of installed cooperative customers, and more.

5.7 Bidding Method

Bid submission mailing address: Bidding & Procurement Office, Leshou Agricultural and Pastoral Group, 3rd Floor, Administration Department, Qilizhuang Village, Leshou Town, Xian County, Cangzhou City, Hebei Province

Contact: Manager Gao: 15530722068

Manager Tang: 18632798771

6. Schedule

Our company will, by 2022 Year 4 Month 23 The bidding documents will be published on the Leshou Group’s official website and WeChat official account, and also sent to all prospective equipment suppliers. Bidding companies are requested to: 2022 Year 4 Month 29 Recently, as required by the tender documents, we submitted the bid documents, company qualifications, and other relevant materials either on-site or via mail to the company. The company is scheduled to… 2022 Year 4 Month 30 Saturday morning 9 The bidding process—including bid opening and evaluation—is conducted online via the Haoshitong software.

 

 

 

HeShou Agricultural and Pastoral Group Co., Ltd. – Hebei Branch

2022 Year 4 Month 23 Day

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Attachment 1 Bidding Requirements for Heating and Air Conditioning Renovation of Leshou Agricultural & Pastoral Group Office Building

1 Bidding companies shall independently design and provide quotations based on the requirements of the "Leshou Agricultural & Pastoral Group Office Building Heating and Air Conditioning Renovation Plan," as well as the site’s existing terrain.

2 The bid price includes all costs associated with completing this construction project—such as ground cutting, waste removal, earth excavation and backfilling, well drilling, pipeline installation, sump pit construction, pipeline crossings, as well as equipment installation and renovation—and covers every aspect of labor, machinery, materials, management fees, site-specific measures, profit, and taxes.

3 Bid-winning method: After evaluation by the Bid Evaluation Committee, the contract was awarded to the bidder offering the most reasonable and lowest price.

4 Payment Method: Upon completion of the project and acceptance by Party A, and after Party B provides the full invoice for the total project cost, Party A will make payment to Party B. 95% Construction payment, representing the remaining portion of the total project cost 5% As a warranty deposit, it will be fully paid two years after Party A approves the acceptance, provided there are no quality issues during this period.

5 The warranty period is two years, during which any quality issues will be repaired and maintained free of charge.

6 Other: Bidding companies are responsible for conducting their own site surveys. Upon completion of construction, they will provide as-built drawings and relevant visual documentation. Additionally, they will supply user manuals and undertake training for on-site operators.

 

Attachment 2 : Comprehensive Renovation Plan for Heating and Air Conditioning in Leshou Agricultural & Pastoral Group Office Building

Ground-source heat pump: buried pipe installation (well-point layout), collection pipe laying, sump well installation, main pipeline crossing into the machine room, and machine room renovation.

1 • Well site selection (see the diagram below for details):

A , the open space between the feed production workshop on the north side of the preferred office building and the northern perimeter wall of the workshop A District).

b If the above space does not meet the requirements, the eastern plot can be utilized instead. B District).

c If the above-mentioned space does not meet the requirements, the plot of land on the east side of the feed production workshop can be utilized instead. (C District )

2 • Pipeline crossing:

From the sump well, cross to the southern edge of the wellpoint layout, then head north toward the machine room and enter the facility.

3 • Data center renovation:

Utilize the existing heat pump units, remove the original water-source equipment, and install a ground-source circulation pump along with the corresponding配套 piping components.

 

 

 

Tags: